Hi Randy,

Here's my estimate for barricades:

3 tree piles X 12 barricades = 36

400 foot perimeter / 8 foot barricade = 50

Total barricades required is 86.

Here's when we need them available:

Dec 26/04   -    12
Dec 31/04   -    24
Jan  7/05    -     50

It's your call whether to have them delivered all at once or on some other schedule that meets the above timetable.

Please advise. Thanks.

Don